Mining Sector Reform in India: Mining Leases with Pre-embedded clearances
08062020 
- Rajesh Deoliya  
[rajeshdeoliya@gmail.com] 
To attract the investment in the mining sector, Government of
  India and State Governments are doing mammoth work to erase the hurdles in
  the way of commencement of mining operations. In recent past government of
  India has brought about several amendments in Mines and Mineral (Development
  and Regulation) Act-2015, Minerals (Other than Atomic and Hydro Carbons
  Energy Minerals) Concession Rules- 2016 and also in the Environment (Protection)
  Act,1986.These reforms will certainly help in bringing new investment because
  a project proponent or successful bidder is assured about the support of
  respective state government and it's authorities in commencement of project
  within the stipulated timeline.   
It is a fact that the contribution of mining sector in the GDP and employment is almost decreasing due to lack of new investment. According to the Federation of India Mineral Industries (FIMI), which in a report states that the mining industry’s contribution (excluding petroleum and natural gas) to India’s GDP in 2018/19 was pegged at 1.63%, down from a peak of 1.93% in 2012/13. In comparison, mining contributed 7.5% to South Africa's GDP and 6.99% to Australia's GDP. (Source: Mining Weekly, 27th January,2020) This is because we are not able to bring virgin areas into production. 
To attract investment in the mining sector, year 2015 onward
  drastic changes in the procedure of allocation of mining lease were made. The
  then existing preferential right (First cum First Serve) clause in grant of
  mineral concessions was scrapped for buoyant auction of mining lease. This change
  brought transparency in the grant of mining leases and assured premium to
  government in terms of revenue generation but the high payments to government
  in bidding  and delay in the projects
  due to delay in grant of permissions, approvals and clearances made things
  worst in favour of successful bidders.  
The government has realized the issues and came up with an amendment by an order of Ministry of Mines, Government of India dated 03.06.2020 paving way for grant of some of the mining leases having pre-embedded clearances for mining projects (lease). Initially this will be a pilot project i.e each state government will identify 5 mineral blocks in pre-embedded mode and others in normal auction mode in which all the clearances will be obtained by successful bidder.  | 
 
The Pre-embedded clearances: 
In general, the auction blocks require following clearances/
  permissions for commencement of mining operation: 
1.    Forest Clearance 
2.    Wild life clearance/ The NoC from Wild Life
  Conservator of Forest.  
3.    Mining Plan
  approval 
4.    Environmental
  clearance 
5.    Consent to
  Establish 
6.    Consent to Operate 
7.    Explosive license 
8.    Mine
  opening permission 
9.    Permission for installation / trail
  operation of equipment 
10.  Ground water
  clearance 
11.  Railway Siding
  approval 
12.  Power line from
  state DISCOM 
13.  Approval for diesel
  storage 
14.  Clearances related
  to the work under an existing transmission line or  
       shifting of the transmission line 
15.   Gram Sabha consent 
16.   NoC from Panchayat 
Apart from these some more permissions are also required which
  may also be part of pre-embedded clearances  
17.  Aravali Certificate
  ( applicable in Aravali Hill range areas) 
18.  NoC from revenue
  records. 
19.  Transfer of
  Government land and falling in the mining lease are 
20.  DGMS Permissions 
21.  Approval of
  Rehabilitation / Resettlement plan 
22.  Social Impact
  Assessment studies 
23.  Land Acquisition. 
24.  Stoppage of sale or
  purchase of land in the mine block area to protect the interest of successful
  bidder. 
 | 
 
The Project Monitoring Unit (PMU): 
In the newly proposed system pre-embedded permissions for a
  mine block will be arranged by a PMU which will engage subject experts to
  obtain permissions like approval of mining plan, environmental clearance, forest
  clearance etc. The PMU will arrange the land rights for government as well as
  private land which will be transferred to successful bidder.  
The expenditure incurred by PMU / state government in
  obtaining clearance will be charged from the successful Bidder. 
 | 
 
The Pre- caution: 
Since the PMU will be a government body and project will be
  undertaken by a private body, precautions have to be taken in design of
  project concept and project budget. A project seems viable to PMU may not be
  viable to bidders. 
ii) Issues of Project Concept and Viability:  
The PMU has to do some preliminary work related to the project
  concept and its viability. Say for example, the mining plan and environmental
  clearance are production and technology specific, these are decided by a
  project proponent based upon his experience with technology, market
  conditions, financial capabilities, short term and long term business
  planning etc, for entire mine life. In the absence of such knowledge, the
  project concept designed by PMU may not be encouraging to project proponent
  and rather may result in distraction. 
iii) Issues in Production Design:  
The successful bidder may require change in the mine
  production immediately or after some time. The restriction of liberty of 25
  percent change in the mine plan production is a limitation because if PMU
  takes clearance at high production than it will be almost difficult for
  project proponent to modify the business plan. A general tendency of a
  project proponent is to keep mine production at minimum possible level for
  first five year and then increase it in subsequent plan period in such a way
  to extract the entire mineral in the remaining life of mine. Approaching
  MoEFCC for change in production will again result in delay. For higher
  production the state government may not raise any objection but for lower
  production planning by successful bidder, the state government may not agree
  because of anticipated loss of revenue and changes in the Mine Development
  and Production  Agreement (MDPA) which
  is essential part of mine lease deed. Since the mine blocks are of commercial
  nature a bidder may not find ample orders for disposal of higher mineral production
  in the market. This will attract penalties, appropriation of performance
  securities which may lead to cancellation of mine too. If successful bidder
  decides for captive use then also the pre-decided production parameters may
  not be attractive.  
iv) Issues of Public Commitments: 
In public hearing the state government will do all the
  commitments on behalf of project proponent because project proponent will not
  be part of public consultation process which may result in conflict between
  successful bidder and community. This can be avoided by reasonable
  commitments and giving liberty to the successful bidder to modify commitments
  upon interaction with the community once project commences.   
 | 
 
The Conclusion: 
The above discussion may appear negative but it is only about
  pre-cautions in deciding the project parameters for pre-embedded mine blocks
  in such a way that they are attractive to the bidders and achieve the goal of
  extraction of minerals from mine blocks. The pre-embedded mine blocks are
  expected to get good response. The process will save time in commencement of
  mining projects and deal with the issues of development of backward areas. Since
  government is involved in obtaining the clearances, the community may find
  the project more trustworthy and support it. The  success of these mine blocks will open the doors
  for government participation in other development projects also. So this is a
  welcome move by the government. 
*** 
Note:
 Readers are requested to share their thoughts and post in the comment 
box of  
           this blog to improve the content for the benefit of society.  IT is also requested to  
           share with those who are interested in the development of mining industry. 
Disclaimer:  The views expressed here are of writer only and do not belong or express  
                    views to any organization, person associated with. 
 | 
 

Comments
1. The level or reliability of State Govt data on Feasibility aspect? State will also provide land for Plant construction ..?? It's not clear.
2. The bidder now needs to go very concieously once after detailed analysis of the project since the Govt will make R& R plan , PH replies, EIA on his behalf.
3. My worry is - now auction process will get more delayed due to lack of manpower with State and land acquisition is also to be done by State.
Overall it's a good move ...let's hope for the best ..
I also have the same concerns as you & Mr. Amit.
Now the State Government has to engage professionals to carry out these work, which seems to be a time taking considering lengthy government procedures.
The quality of all reports are to be watched.
But yes, sure of one thing that we will be moving from conventional to highly professional.
Rather I should thank you for writing this blog in very simple language.
subsequent relative comments from Mr Amit regarding feasibility report prepared by State Govt. and land requirements not only for plant establishments but the rail line connectivity most importantly in terms of logistics should be the part of pre embedded requirements for the project.
The Casino. 12 Casino Drive, Uncasville, CT 06382, United States. Driving 울산광역 출장마사지 Directions. 김제 출장안마 Directions to The Casino - 수원 출장마사지 Uncasville, 광명 출장샵 CT. Directions to 세종특별자치 출장마사지